RFQ Schedule
|
Date Due
|
Responsibility
|
Issue RFQ
|
Novembe15, 2011
|
Authority
|
Questions & Clarification Requests Due
|
November 29, 2011
|
Offerors
|
Post Responses to Questions
|
December 8, 2011
|
Authority
|
SOQs Due
|
December 19, 2011
|
Offerors
|
Select Shortlisted Offerors
|
January 19, 2012
|
Authority
|
RFP
Schedule
|
Approximate
Date
|
Responsibility
|
Shortlisted
Offerors Review Draft RFP, One-on-One Meetings
(Anticipated)
|
Jan/Feb 2012
|
Both
|
Issue RFP
|
March 2012
|
Authority
|
Proposals Due
|
September 2012
|
Offerors
|
Anticipated Contract Award
|
December 2012
|
Authority
|
The following table
summarizes the anticipated schedule of events for Project implementation.
Project
Schedule
|
Approximate
Date
|
Responsibility
|
Notice to Proceed
|
December 2012
|
Authority
|
Project Completion
|
April 2016
|
Design-Builder
|
FRA-approved ICS Project Report
|
September
30, 2017
|
Authority
|